We had a lot of activity at the job site this morning. The carpenters came out to load up their equipment since they are done with their part of the job. The plumbers came in to work on hooking up the water heaters, outside faucets, and all of the drain pipes. They should be done with everything except finish work later on. The drywallers showed up, three to hang drywall and two to start taping and patching joints. The electrician was also scheduled to come in later this afternoon to work on the service panel. We also had the painter here this morning to paint the hard to reach areas of the exterior walls and overhangs before the SkyTrack left the property.
We will start our painting chores next Tuesday as the drywall boss said he will be done with our side of the first floor by then.
Hope all is well with everyone!!